Missões Consortium wins lot I

Fonte: ANEEL
The Missões consortium won Lot I from the Transmission Auction No. 07 / 2013 , conducted by the National Agency of Electricity ( ANEEL ) on Thursday (11/14 ), for R$ 16.2 million, with a negative goodwill of 29.99 % in relation to the initial Permitted Annual Revenue (RAP)of R$ 23.2 million established by the Agency. RAP is the revenue that the entrepreneur is entitled for the provision of transmission service from the commercial operation of the facility.

Lot I consists of three lines and two substations located in the states of Rio Grande do Sul and Santa Catarina. The goal is to expand the core network to improve services to the neighboring municipalities of Pinhalzinho, in Santa Catarina. The project is expected to generate 888 direct jobs, and is scheduled to go into commercial operation in 48 months.

The previous lot "H", composed by Jupari substation located in the state of Pará, had no interested parties in coming and should be announced in the next events to be held by the Agency.