Fonte: ANEEL
The final version of the 006/2008 auction public announcement for the National Interconnected System (SIN) Basic Network’s transmission installation tender was approved today (9/2) by the Brazilian Electricity Regulatory Agency’s (Aneel) collegiate board. Projected for October 3 of this year, the auction will offer concessions for six transmission lines with a total estimated extension of
The tendered installations will be located in the states of Piauí, Maranhão, Minas Gerais,
The main change in the public announcement in relation to prior tenders is the inversion of phases, which consists of legal, technical, economic-financial and fiscal approval after holding the auction. In the phase preceding the auction, the only requirements will be the registration documents and confirmation of participation by interested parties by means of the financial guarantee deposit demanded in the process.
In the specific case of Lot F, the public announcement states the need to transfer to the transmission firm that wins the Missões (RS) substation tender, which belongs to the Rio Grande Energia S/A (RGE) distributor, which will become part of the Basic Network. The operation foresees indemnification for installations and equipment.
For Lot G, the document also determines acquisition by the winner of a section of a double circuit transmission line section about
According to the public announcement timeline, registration documents and guarantee deposits shall be made on October 1. The list of companies able to participate in the auction will be released on the 2nd, the day before the auction. Delivery of documents for the post-qualification of winners will occur on the 8th of that month. The concession contract signing date will be defined in a timely manner.
The public announcement text results from the 27 contributions presented by six companies in the document public hearing process held by Aneel last August 13-20. The public announcement, timeline and other documents related to the tender shall be available at www.aneel.gov.br, through the link Espaço do Empreendedor/Licitações/Editais de Transmissão.
The list of lines and substations included in the auction is shown below:
LT Ribeiro Gonçalves –
SE Balsas, at 230/69 kV (100 MVA)
Approximate extension:
Location: Piauí and Maranhão
Maximum Annual Revenues Permitted: R$ 8.613 million
Projected commercial operation start-up: 18 months
SE Miranda II, at 500/230 kV (450 MVA)
Location: Maranhão
Maximum Annual Revenues Permitted: R$ 7.855 million
Projected commercial operation start-up: 22 months
LT Bom Despacho 3 – Ouro Preto 2, at 500 kV,
Approximate extension:
Location: Minas Gerais
Maximum Annual Revenues Permitted: R$ 11.146 million
Projected commercial operation start-up: 21 months
LT Porto Alegre 9 –
Approximate extension:
LT Porto Alegre 9 –
Approximate extension:
LT Nova Santa Rita –
Approximate extension:
LT Monte Claro – Garibaldi, at 230 kV
Approximate extension:
Location:
Maximum Annual Revenues Permitted: R$ 9.074 million
Projected commercial operation start-up: 24 months
SE Narandiba, at 230/69 kV (200 MVA)
Location:
Maximum Annual Revenues Permitted: R$ 10.367 million
Projected commercial operation start-up: 24 months
SE Missões, at 230/69 kV (150 MVA)
Location:
Maximum Annual Revenues Permitted: R$ 3.254 million
Projected commercial operation start-up: 16 months
SE Suape II, at 500/230 kV (600 MVA)
SE Suape III, at 230/69 kV (200 MVA)
Location: Pernambuco
Maximum Annual Revenues Permitted: R$ 14.989 million
Projected commercial operation start-up: 24 months