Fonte: ANEEL
The board of the National Enegy Agency (ANEEL) conducts tomorrow (03/04) the 2nd Extraordinary Meeting of 2011. On the agenda, seven cases of Declaration of Public Utility (DUP) of areas of land used for conducting power transmission lines and the installation of substations will be deliberated. Check below the list of areas that should receive the DUP.
Benefited company | Venture | Location | Extent of declared area |
Linhas de Transmissão do Itaim Ltda. | Chapadão-Costa RicaTransmission Line | Cassilândia, Chapadão do Sul and Costa Rica, in Mato Grosso do Sul | 108km |
Linhas de Transmissão do Itaim Ltda. | Chapadão-Porto das ÁguasTransmission Line | Cassilândia (MS) e Aporé and Chapadão do Céu (GO) | 62 km |
Linhas de Transmissão do Iatim Ltda. | Chapadão-GuatambuTransmission Line | Cassilândia (MS) | 33 km |
Linhas de Transmissão do Itaim Ltda. | Guatambu-NardiniTransmission Line | Cassilândia (MS) and Aporé (GO) | 50 km |
Companhia Hidroelétrica do São Francisco (Chesf) | Teixeira de Freitas II Substation | Teixeira de Freitas (BA) | – |
Transenergia Renovável S/A. | Jataí-Água EmendadaTransmission Line | Jataí and Perolândia (GO) | 32 km |
São Pedro Energia S/A. | Sectioning Substation of Ibis-GuarapariTransmission Line | Viana (ES) | – |