ANEEL transfers Imbé I SHP authorization and redefines work timetable

Fonte: ANEEL

At its last meeting on March 22, the Brazilian Electricity Regulatory Agency board approved transferring the authorization to exploit the Imbé I Small Hydroelectric Plant, as an independent producer*, from Construtora Preart Ltda. to Paracatu Energia S/A. The Imbé I SHP has 2.3 Megawatts of installed capacity and it is located on Preto River, in the municipality of Imbé, Minas Gerais (MG).

Upon analyzing the transfer of ownership, the Agency checked issues that refer to legal qualification and fiscal good standing requested of Paracatu Energia and it determined demands were met. Since the plant’s timetable was behind schedule, new milestones were presented for implementing the SHP, which should begin commercial operations on February 1, 2014. (DB/GL)

 
Action
 
Deadline
 
Begin setting up the job site and camp
 
 
September 1, 2011
 
Begin civil works for structures
 
 
October 1, 2011
 
Deviate the river
 
 
December 1, 2011
 
Begin concreting the power house
 
 
April 1, 2012
 
Begin electromechanical assembly
 
 
September 1, 2012
 
Begin transmission line construction
 
 
March 1, 2013
 
Obtain Operating License
 
 
February 1, 2014
 
Fill the reservoir
 
 
February 1, 2012
 
Begin test operations of generating units
 
 
January 1, 2014
 
Begin commercial operations of generating units
 
 
February 1, 2014