Fonte: ANEEL
Company Transmissora Aliança de Energia Elétrica S/A (TAESA) was authorized by the National Energy Agency (ANEEL) to achieve reinforcement of their facilities to improve care of energy supply in the Northeast region. This decision came at the Board Meeting held last Tuesday (06/07). The board authorized improvements at two substations located in Bahia. To pay for those investments, TAESA shall be entitled to installments of the Annual Revenue Allowed (RAP)*, of BRL 9.22 million. Check below the reinforcements and the values of the RAP.
Venture |
Value of the RAP (BRL) |
SE IBICOARA Adequacy of the arrangement of the bus of the yard at 500 kilovolts (kV). |
1,728,905.75 |
SE SAPEAÇU Installation of a Static Compensator of 230 kilovolt (kV). |
7,498,080.06 |
Total |
9,226,985.81 |