Reinforcements in MG transmitter receive authorization from the board

Fonte: ANEEL

The Brazilian Electricity Regulatory Agency (ANEEL) authorized Sete Lagoas Transmissora de Energia Ltda. to reinforce its transmission installations.Reinforcements will be installed at the Sete Lagoas 4 substation. In order to pay for the investment, the company will have the right to Permitted Annual Income (RAP)* installments worth R$ 491 thousand.This decision was made at the Agency’s collegiate board meeting held last Wednesday (11/16). Check out the reinforcements and RAP sum below.

Enterprise RAP (R$ – Jun/11)
SE Sete Lagoas 4
Installation of a capacitor in derivation and associated connection module.
491,159.73