Fonte: ANEEL
The board of the National Energy Agency (ANEEL) approved on Tuesday (02/07), statements of public utility (DUP) of lands for construction projects located in Mato Grosso, Rio Grande do Norte, São Paulo and Minas Gerais.
In Mato Grosso, the DUP was in favor of Centrais Elétricas Matogrossenses S./A.(Cemat) for deployment of the first section of Sapezal-Comodoro Distribution Line, simple circuit, 138 kilovolt (kV) substation that will interconnect the Sapezal structure No. 266 of the line.The section is located in the municipalities of Sapezal and Julio Campos.
In Rio Grande do Norte, the declaration was in favor of Companhia Energética do Rio Grande do Norte (Cosern) for passage of the Natal III- Passagem de Areia distribution line, 69 kV, located in the municipalities of Macaíba and Parnamirim.
Company Energia Caiuá S. / A.(Enercasa), however, received a DUP for passage of the transmission line between Thermal Power Plant (TPP) Decasa and the sectioning of the Assis/Canoas II transmission line, in the nominal voltage of 88 kV, in the municipality of Ibirarema (SP).
And, in the state of Minas Gerais, it was approved the DUP in favor of Companhia Energética de Minas Gerais (Cemig) for passage of the Araçuaí 2- Itaobim transmission line, in the nominal voltage of 138 kV, located in the municipalities of Araçuaí, Itinga and Itaobim. (PG/BT)