The Brazilian Electricity Regulatory Agency (ANEEL) approved an edict for Public Call no. 01/2012 to identify those interested in sharing Transmission Installations of Exclusive Interest to Generation Plants for Shared Connection (ICG)* in the states of Ceará and Bahia.The call will be for those sellers who sold wind energy in auction no. 07/11 (A-5) held in December 2011. The decision by the Agency’s collegiate board this Tuesday (5/2) is for the call to be held May 15 and 16, 2011.
These installations will function as energy collector stations produced by the wind energy plants installed in each ICG's area of operation.The public call projects three collector stations, two in Ceará (Arati II and Cruz) and one in Bahia (Campo Formoso).
The Agency’s decision delegates part of the call for proposals’ operationalization to the Electric Power Commercialization Chamber.The main functions of the CCEE in this call are:the contracting of a custodial agent for guarantees of participation, capable of executing activities in Brasília and São Paulo and the execution of all activities that refer to control of delivery, extension and release of guarantees.(DB/PG)
*TRANSMISSION INSTALLATIONS OF EXCLUSIVE INTEREST TO GENERATION PLANTS FOR SHARED CONNECTION (ICG)– Transmission installations and equipment, not part of the BASIC GRID and the other transmission installations, for shared access of generation plants using wind, biomass or small hydroelectric plants connected to the basic grid.