Fonte: ANEEL
The start of a public hearing to discuss the preliminary proposal of the Third Rate Revision (RTP) of Força e Luz de Urussanga Ltda.(EFLUL) was approved today (05/15) by the National Energy Agency(ANEEL), it will take effect from August 14, 2012. The hearing will receive input from stakeholders in the period from 05/17 to 06/17.
Check below the average preliminary approval for the company:
Company | Average preliminary effect | Area served |
EFLUL | 3.97% | City of Urussanga (SC) |
In the revision of the concessionaire, we applied the methodologies adopted in November to the 3rd cycle. The Periodic Rate Revision process is meant to examine, after a previously defined period in the concession contract (usually four years), the economic-financial balance of the concessionaire. It also approved the new limits for power quality indicators (DEC * and FEC **) of the concessionaire for the period from 2013 to 2016.
Check below the deadlines and email addresses for contributions:
Deadline for contributions | E-mail for contributions | Date of Onsite Meeting |
AP of the Rate Revision: 05/17 to 06/17 |
Rate Revision: ap033_2012rv@aneel.gov.br Rate Structure: ap033_2012et@aneel.gov.br Technical Losses: ap033_2012pt@aneel.gov.br |
06/15 in Urussanga (SC), in time and location to be announced later.. |
AP of the DEC and the FEC: 05/17 to 06/17 | ap033_2012ic@aneel.gov.br | Together with the RTP onsite meeting. |
Contributions can also be sent by fax to (55 61) 2192-8839 or to the address of the Agency (SGAN, Quadra 603, Módulo I, Térreo, Protocolo Geral, CEP: 70.830-030), in Brasília (DF). (VS/PG)
* Duration of Interruptions per Consumer Unit – DEC – Time interval in which, on average, during the observation period, in each consumer unit of a given group, there was discontinued distribution of electricity. Refer to Prodist Module I.
** Frequency of Interruptions per Consumer Unit – FEC – number of interruptions that occurred on average during the observation period, in each consumer unit in the group considered.